Work update
End of March '01
-
From the 1,400 golden disks needed
to cover the entire structure, presently 1,100 discs are
ready. Of these, 685 are already mounted, reaching down to
the equator of the structure.
-
All around the equator, stainless
steel catwalks are to be fixed (well hidden behind the
disks) for future cleaning and maintenance purposes. The
catwalks are being fabricated on site and will be fixed
during April, after which the mounting of the discs below
the equator can proceed.
-
Modeling work is ongoing to finalise
the special gilded features that will highlight each of
the four main entrances to Matrimandir.
-
Several new test-panels of
salmon-pink glass have been placed in the inner skin of
the sphere for final evaluation. We will also do some test
triangles (each 3 mtr wide x 2.4 mtr high) using imported
extra-clear glass to see if a superior colouring is
obtained.
-
The marble work inside the
structure, on the 1st and 2nd levels and the central
staircase, progresses steadily.
-
Red stone cladding has begun on the
10th and 11th petals, starting from their bottom lines,
which are near the circular pool directly underneath the
structure.
-
Dozens of new air-roots are growing
rapidly down from the branches of the Banyan Tree in the
MM Gardens. They are enclosed in plastic tubes filled with
compost, and are watered regularly to help them grow well.
These new air-roots will help to support the many branches
of the tree, some of which are very old and beginning to
lose their strength.
-
The Matrimandir Nursery celebrates
this season of flowers with orchids, plumeria, hibiscus
and others in magnificent bloom.
|
|